Planning Solar Around a Roof Replacement

Last updated By The SolarPanelFinder Rooftop Desk

If your roof is near the end of its life, replace it before the solar panels go up, then have the array installed on the new roof. Put that order of work into both contracts, so no crew has to come back and be paid twice.

Plan for two trades. Only 4 of the 161 companies in this index are filed under Solar Roofing, and none of those 4 is also filed under Solar Panel Installation, so a homeowner using this index will usually hire a roofer and a solar installer separately.

Why does the roof come first?

Because the array sits on top of the roof for as long as the panels last. Natural Resources Canada describes well-functioning solar systems as having an expected lifetime of 25 years or more. A roof that needs replacing partway through that period brings a solar crew back to take the array off and put it back on.

That second visit is a separate job with its own price, its own electrical work and its own schedule. Replacing a tired roof first avoids it. The roofer works on a bare roof, and the solar installer mounts the array on new shingles over a deck that has just been checked.

The judgement call is how worn is too worn, and this guide does not set a number. Ask a roofer to inspect the roof before you collect solar quotes, and to give you their view of its remaining life in writing, with photos. The guide to home insurance and rooftop solar covers what insurers say about older roofs.

Who in the index handles both roofing and solar?

Very few companies. The index files 4 of its 161 companies under Solar Roofing. The same 4 are the only records that carry Google's Roofing contractor business label. None of them is also filed under Solar Panel Installation, the category that holds 143 companies.

Here is what each record and each company's own website show:

  • Sunrise NRG, Richmond Hill: its own website says it offers roofing and solar work, whether a roof upgrade, a solar installation or both. The site kept it after a wrong-trade report for that reason.
  • Eco-Tech Roofing Solutions, East York address in Toronto: the site filed it under Solar Roofing because its website has a Solar Applications section.
  • Sands Solar Roofing Inc., Thornhill address: its website answered with a page-gone error in the site's 26 August 2026 link check and again on 16 November 2026, so the listing does not link to it.
  • Ontario Roof Consultants, Ajax: its own website describes roof consulting work that includes supervising roof replacements done before solar installations.

You can see them together on the solar roofing category page. A company that sells both trades still has to answer the questions later in this guide, starting with which parts its own crews do and which it hires out. Where no single company does both, the job is two contracts with two trades, and the homeowner sets the order.

What does the roof itself cost in Toronto?

One GTA roofer's published Toronto figures give a starting point. AUK Roofers, which says its numbers come from its own Toronto install records, puts a new roof on a typical Toronto detached home at $8,800 to $16,500 in architectural asphalt shingles. It adds that plank decking on homes built before 1970 often needs full sheathing replacement, which it prices at $4,200 to $8,800 more. The deck is the layer of boards under the shingles.

These are one seller's figures, last reviewed 3 June 2026, so treat them as a guide, not a quote. AUK's page does not say whether they include the harmonized sales tax (HST), which the Canada Revenue Agency lists at 13 percent in Ontario, so ask any roofer whether the HST is in the total. The solar roofing cost guide sets AUK's other house sizes beside metal roofing and solar shingles, and the guide to what a solar quote leaves out shows where the roof sits among the other costs a solar quote may not cover.

What does it cost to take panels off and put them back?

This guide found no published Canadian price for removing and reinstalling a solar array. Search results for this job are full of American per-panel rates. They are left out here, because American labour and permit costs do not carry over to a Toronto roof.

That gap matters most when the array is already up. If you are in that position, ask the company that installed it to quote the job in writing, with these as separate lines:

  • taking the panels and racking off the roof,
  • storing them safely while the roofer works,
  • putting them back and resealing every roof mount,
  • reconnecting the wiring and arranging the electrical inspection.

If the original installer has closed or will not return, ask another solar company to quote the same lines; the solar panel installation category shows 12 of the 143 companies filed for that work. Get the roofer's schedule first, so the solar crew's two visits sit either side of the reroof.

In what order should the two trades work?

Roof first, then the solar paperwork, then the array. For a Toronto home served by Toronto Hydro, this order fits the published rules, which put the utility agreement and the electrical notification before the work starts; write it into both contracts:

  1. Roof inspection. A roofer checks the shingles and the deck and says in writing how long the roof has left.
  2. Reroof, if needed. Any deck repair happens now, while the roof is bare.
  3. Building permit. The City of Toronto requires a building permit for solar panels with an area greater than 5 square metres on rooftops. Its guide asks for structural calculations by an Ontario registered engineer that verify the roof framing, though it says manufacturer's information may sometimes be substituted.
  4. Utility connection request. For systems of 12 kilowatts (kW) or less, Toronto Hydro asks you to request a connection and sign a connection agreement before construction starts.
  5. Electrical notification. The Electrical Safety Authority (ESA) says the person doing the work should file a notification of work before the work starts. It adds that a building permit is not the same thing, and you may need both.
  6. Installation and inspections. The array goes on and ESA inspects the electrical work. Toronto Hydro then does its own site inspection and, if applicable, installs a new meter.

Outside Toronto, the city and the local utility set their own steps, and this guide read only the City of Toronto's and Toronto Hydro's. The engineer's calculations are about the roof framing, so hand the solar installer the roofer's inspection report and any invoice for deck work. The guide to the paperwork behind a GTA solar install covers the permits and filings in more depth.

What happens to the shingle warranty once panels go up?

It depends on the shingle maker, and at least one maker limits its cover. IKO's limited warranty for shingles installed in Canada on or after February 1, 2025 excludes "any damage that arises after the roof is altered following the original" installation of the shingles. Its list of alterations includes "equipment installations", with examples that include solar heaters and "equipment or machinery of any kind".

The same warranty excludes damage from failure of the roof base, including conditions arising when shingles are laid on "dimensional lumber, shiplap or board decks". That is one more reason to deal with an old plank deck during the reroof. Other shingle makers write their own terms, and this guide has read only IKO's.

The index holds no warranty terms for any listed company. So these questions belong in writing, to both trades:

  • Does the shingle warranty on this roof exclude rooftop equipment?
  • Does the solar installer's workmanship warranty cover leaks at the roof mounts, and for how long?
  • If water comes in near a mount, who comes out first?
  • Will the roofer hand over the shingle warranty document, with the installation date, before the array goes on?

Who can disconnect an existing array?

An electrical contractor licensed in Ontario, which a roofer may not be. Taking an array off a roof means disconnecting its wiring and later reconnecting it. The ESA says "The only way to be sure electrical work is safe and legal is to hire a Licensed Electrical Contractor (LEC)", and that an LEC will file the notification of work.

The ESA also says Ontario's electrical code requires almost all electrical work to be reported through a notification of work. Ask the solar company who files it for the reconnection, and ask for the inspection result when the array is back up. The index does not check licences, so ask each company for its ESA licence number before it touches the wiring. The guide to who does the electrical work on a solar install explains the roles, and the guide to solar shingles or panels on a Toronto roof compares the two options if you are reroofing anyway.

Frequently asked questions

Should I replace my roof before installing solar panels?

If the roof is close to the end of its life, yes. The array sits on top of the shingles, so a reroof after installation means paying a solar crew to take the panels off and put them back. Ask a roofer to inspect the deck and shingles first, and get their view of the roof's remaining life in writing before you collect solar quotes.

How much does it cost to remove and reinstall solar panels for a new roof?

This guide found no Canadian source that publishes this price, and it left out the American per-panel figures that fill search results. Ask the company that installed your array to quote removal, storage, reinstallation and the electrical reconnection as separate written lines, and ask who files the electrical notification for the reconnection.

Can one company do both the roof and the solar in the GTA?

At least one says it can: Sunrise NRG's own website offers a roof upgrade, a solar installation or both. This index files 4 companies under Solar Roofing: Sunrise NRG in Richmond Hill, Eco-Tech Roofing Solutions in East York, Sands Solar Roofing Inc. in Thornhill and Ontario Roof Consultants in Ajax. None of the 4 is also filed under Solar Panel Installation, so ask each one which parts of the job its own crews do and which it hires out.

Does a solar array affect my shingle warranty?

It can. IKO's limited warranty for shingles installed in Canada on or after February 1, 2025 excludes damage that arises after the roof is altered, and it lists equipment installations among those alterations. Other makers write their own terms. Read the warranty for the shingles on your roof, and ask the solar installer in writing what its workmanship cover says about leaks at the mounts.

Sources

Each figure below is stated by the source named after it.